Sopal Tools

Research and calculators for Security of Payment work in QLD, NSW and VIC.

Research Agent

Answers Security of Payment questions from the legislation, Sopal’s decisions and the courts’ judgment databases, with primary sources cited.

Research Agent

Research AgentQLD · NSW · VIC · Cth

When must a payment schedule be given in Queensland?

  1. legislation search "payment schedule" --qldBuilding Industry Fairness (Security of Payment) Act 2017 (Qld)
  2. legislation read "BIF Act" "s 76"76 Responding to payment claim
  3. decisions search "payment schedule" w/15 "out of time"173 decisions
  4. caselaw search "payment schedule" --court QCACourt judgments

Within whichever of these ends first: the period the contract allows, or 15 business days after the payment claim is given.

Source: Building Industry Fairness (Security of Payment) Act 2017 (Qld) s 76(1).

Due date calculator

Each time limit, with its section. Switch between QLD, NSW and VIC.

Due date calculator

Due date calculatorschedule for less than the claim

Building Industry Fairness (Security of Payment) Act 2017 (Qld)

  1. Payment claimStarts the timetable
  2. Payment schedule15 business days, or earlier under the contracts 76(1)
  3. Adjudication application30 business days after receiving the schedules 79(2)(b)(iii)
  4. Adjudication responseLater of 10 and 7 business days (standard claim)s 83(1)
  5. Adjudicator's decision10 business days (standard claim)s 85(1)

Interest calculator

Interest on a late progress payment, at the rate the Act allows.

Interest calculator

Interest calculatorQLD · BIF Act s 73
RateContractual, 10.00% a year
Days193
Principal$412,860.00
Interest$21,830.68

Flowchart

The process from payment claim to decision. Choose a jurisdiction and click a step for the rule and its section.

Flowchartclick a step

The Research Agent is included with Sopal Decisions and Sopal Workspace.