Payment Schedule

When is the payment schedule due?

Section 76

Adjudication Application

Deadline to lodge the application

Section 79

Adjudication Response

Deadline for the response

Section 83

Adjudicator's Decision

Deadline to deliver the decision

Section 85

Payment Schedule Due Date

s76 BIF Act
Relevant Provision: section 76

76 Responding to payment claim

(1) If given a payment claim, a respondent must respond to the payment claim by giving the claimant a payment schedule within whichever of the following periods ends first--

(a) the period, if any, within which the respondent must give the payment schedule under the relevant construction contract;

(b) 15 business days after the payment claim is given to the respondent.

Relevant Provision: section 79

79 Application for adjudication

(2) An adjudication application--

(b) must be made within--

(i) for an application relating to a failure to give a payment schedule and pay the full amount stated in the payment claim--30 business days after the later of the following days--

(A) the day of the due date for the progress payment to which the claim relates;

(B) the last day the respondent could have given the payment schedule under section 76; or

(ii) for an application relating to a failure to pay the full amount stated in the payment schedule--20 business days after the due date for the progress payment to which the claim relates; or

(iii) for an application relating to the amount stated in the payment schedule being less than the amount stated in the payment claim--30 business days after the claimant receives the payment schedule

Relevant Provision: section 83

83 Time for making adjudication response

(1) If responding to a standard payment claim, the respondent must give the adjudicator the adjudication response within the later of the following periods to end--

(a) 10 business days after receiving the documents mentioned in section 79(4);

(b) 7 business days after receiving notice of the adjudicator's acceptance of the adjudication application.

(2) If responding to a complex payment claim, the respondent must give the adjudicator the adjudication response within the later of the following to end--

(a) 15 business days after receiving the documents mentioned in section 79(4);

(b) 12 business days after receiving notice of the adjudicator's acceptance of the adjudication application.

(3) However, if responding to a complex payment claim, the respondent may apply to the adjudicator for an extension of time, of up to 15 additional business days, to give the adjudication response to the adjudicator.

Standard (≤ $750k)
Complex (> $750k)
Relevant Provision: section 85

85 Time for deciding adjudication application

(1) Subject to section 86, an adjudicator must decide an adjudication application no later than--

(a) for a standard payment claim--10 business days after the response date; or

(b) for a complex payment claim--15 business days after the response date.

(2) The response date is--

(a) if the adjudicator is given an adjudication response under section 83--the day on which the adjudicator receives the response...

Standard (≤ $750k)
Complex (> $750k)

Result

Disclaimer: This calculator is a guide only and should not be relied upon as a substitute for professional legal advice. Public holiday data may not account for all regional variations or future changes. Users must independently verify all dates and deadlines.